Projects
On this page we present interesting, realized projects that give a comprehensive insight into the range of our work. We are convinced that successful projects and satisfied clients offer the best opportunity to convince yourself of the quality of our work.
Project Overview
- steel company
- refinery
- rock salt works
- oil mill
- plant engineering
- chemical company
- pipeline construction
- waste incineration plant
- metal company
- steel pipe company
- steelworks
02.10.2023 – 04.11.2023
Bremen / steel company
Replacement of burners in the blast furnace (60 units, 68t)
Disassembly and assembly:
- Mobile platform
- Compensators
- Plate coolers (staves)
- Openings in the furnace shell
- Compensators, outer surfaces, furnace shell
06.03.2023 – 31.10.2023
Rheinberg / rock salt works
Renovation work on the stoker tower (240t)
- Disassembly and assembly of the old stoker tower
- Assembly of the new stoker tower (42m high)
- Assembly of steel construction, catwalk and platforms
- Relocation of 3 stokers – 6 tons each
20.09.2023 – 12.10.2023
Hamm / oil mill
Replacement of a drying drum (110t, 24m)
Disassembly and assembly:
- Pipes to the bio tank
- Bridges to the heat exchanger
- Connections and pipes to the dryer
- Drive shaft with bearings
01.09.2023 – 31.07.2024
Aschersleben / plant engineering
Steel components and welded structures (180t)
- Manufacture of steel components
- Manufacture of welded structures
- Unloading and loading
01.02.2022 – 30.04.2024
Gelsenkirchen/ refinery
Steel components and pipe bridges (250t)
- Assembly of steel structures
- Assembly of pipe bridges
- Welding work on reinforcements and connections of pipe bridges
- Repair work
01.09.2022 – 31.08.2024
Ludwigshafen / chemical company
Supports and steel structures (90t)
Disassembly and assembly:
- Supports
- Stage structures
- Steel structures
- Welding work
01.02.2022 – 30.04.2024
Meppen / pipeline construction
Steel, pipe and plant construction (70t)
- Manufacture of pipe bridges
- Manufacture of pipelines
- Manufacture of steel construction components
23.05.2024 – 12.06.2024
Hagen / waste incineration plant
Replacement of two cranes (32t)
- Disassembly and assembly work
- Welding work
- Positioning
13.05.2024 – 12.06.2024
Hamburg / metal company
Inspection work on the blower
and compensators (10t)
- Disassembly and assembly work
- Cleaning in the connection and sealing area
- Compacting
- Screwing
- Replacing wearing parts
22.07.2024 – 06.11.2024
Hamm / steel pipe company
Preparatory work for machine assembly (80t)
- Measuring the installation positions
- Installation of foundation frames
- Screwing, aligning and securing
- Protective work against corrosion
22.07.2024 – 06.11.2024
Duisburg / steel works
Duisburg / steel works
Revision work on the primary filter 1+2
- Disassembly and assembly of a cooling chamber
- Dismantling and assembly of a raw gas pipeline (diameter approx. 3500 m and approx. 12 m length)
- Disassembly and assembly of a downpipe (diameter approx. 300 m and approx. 7 m length)
- Disassembly and assembly of explosion flaps
Project details
Installation of technical components such as: flaps, nozzles, transitions and their connections.
Dimensions of the steel structure :
- Individual components weigh approx. 2 to 15 tons
- Pipe diameter in the range of DN 1800 to approx. DN 3500
ab 23.06.25
Disassembly and assembly of a cooling chamber
Normally, we ensure that capacity bottlenecks are bridged and ensure that projects are completed reliably and on time.
The project here in Duisburg has also shown once again that our engineers with their many years of experience are universal problem solvers from time to time.
When the cooling chamber was replaced, it became apparent that it was too heavy for the crane. In order not to exceed the permissible load capacity, it had to be significantly lighter. This was achieved quite simply by burning out – cooling chamber lighter, order carried out – knew how!
Dismantling and assembly of a raw gas pipeline
Through the use of our teams made up exclusively of experts, we help to close personnel gaps at our customers.
We ensure that capacity bottlenecks are bridged and ensure that projects are completed reliably and on time.
Disassembly and assembly of a downpipe
IndMont guarantees the professional execution of the services by employing specialists who are trained in advance on the specific project requirements. The preparation time for an operation usually takes one week.
This enables IndMont to adapt exactly to the customer’s needs.
The employees see themselves as independently working members of well-rehearsed teams. German-speaking foremen ensure smooth communication on the construction site.
Disassembly and assembly of explosion dampers
Here, too, IndMont guarantees professional execution. Training tailored to the specific project requirements is a matter of course and allows very short preparation time. We usually calculate with one week.
This allows IndMont to adapt to the requirements of its customers at all times.
Project Overview
- steelworks Kapfenberg
- steelworks Linz
- rolling mill
20.04.2020 – 30.11.2023
Kapfenberg / steelworks
Expansion and commissioning
of a production line for cast parts
for wind turbines (350t)
Complete assembly (welding work)
- Blower house in gas cleaning plant (32m height)
- Cooling chimney and converter,
- Ladle Furnace
03.04.2024 – 31.10.2024
Linz / steelworks
Steel construction pre-assembly for a lifting basket
and new system components (360t)
- Disassembly and assembly work
- Welding work
13.05.2024 – 31.07.2024
Weinburg / rolling mill
New assembly of a rolling mill (410t)
- Assembly of all parts
- Measurement, piping and cabling
- Trial operation
from 11.08.25
Hamburg / steelworks
Dismantling/installation of ventilation ducts, in connection with dedusting and ventilation in a steel mill.
- Assembly of a casting tundish including all components (steel construction, pipelines, connecting elements)
- Set up of the load-bearing steel structure (frame) with the help of cranes
- Lifting and precise alignment of large segments of the casting tundish.
- Screw and welded connections – assembly of brackets, brackets and connecting parts
Installation of technical components such as: flaps, nozzles, transitions and their connection.
Dimensions:
- Weight of the steel structure: individual components weigh approx. 2 to 15 tons
- Pipe diameter is in the range of DN 1800 to approx. DN 3500